DEBARI TO UMRAH WORK DUE
2.
#POLE* BERACH TO FATEHNAGAR POLES 98% FIXED
* FATEHNAGAR STATION POLE FIX PENDING WORK
* FATEHNAGAR TO MAVLI POLES FIX PENDING WORK
* MAVLI TO UMRAH WORK DUE
3.
#WIRE* GSD & KAPASAN SATION WIRING WORK COMPLETED
* BERACH TO FATEHNAGAR WIRING WORK PENDING
ALMOST 70% WORK COMPLETED