– 19.99 Cr.
✳️ Overall Physical Progress – 78%
✳️ Scope of work-
➡️ Down Yard- Increase in length of reception & dispatch lines of down yard line no 1, 2, 3 upto 844 mtr.
➡️ Extension and widening of PF No. 1 & 2.
➡️ Increase in length of reception and dispatch lines of UP yard line no 4, 5, 6.
➡️ Dismantling and Reconstruction of ROB (Road over bridge)
✳️ Completed works-
➡️ Platform Covershed work completed for 124mtr (on Igatpuri end), 144 mtr (on CSMT end )
➡️ Launching of purlins completed.
➡️ The work of micro piling & pile caps in approaches is completed.
✳️ Work In Progress –
➡️ Dismantling and reconstruction of Road Over Bridge (ROB).
➡️ Extension and widening of Platform.
➡️ Micro Pile construction for earth retention.
➡️ Excavation is in progress for abutments.
🛑Completion of this work will improve mobility of trains in Kasara to Igatpuri section.