A) In progress works-
➡️Basement slab 50% completed. Balance work in progress
➡️Ground level slab shuttering work in progress
➡️Excavation & Foundation work in progress
B) Completed works-
✅West Side cable shifting
✅Soil investigation
✅Site lab commissioning
✅Batching plant installation
✅East Side utility shifting
✅New entry/exit for diversion of traffic
✅Parking area shifting
✅Wheel washing unit installation
CR is committed for gradual improvement of amenities for our passengers.
please wait...Translate to EnglishAdmin #Admin Moderator #Moderator Source Cr X Handle
CRInfraUpdates
Nagpur station major upgrades redevelopment work-
Cost- 487.77 Crores
A) In progress works-
➡️Basement slab 50% done. Rest of the work is ongoing
➡️Ground level slab shuttering work is ongoing
➡️Excavation & Foundation work is ongoing
B) Completed works-
✅West Side cable shifting
✅Soil investigation
✅Site lab set up
✅Batching plant installation
✅East Side utility shifting
✅New entry/exit for diverting traffic
✅Parking area relocation
✅Wheel washing unit setup
CR is dedicated to gradually improving facilities for our passengers.