The Bhaupur-Khurja (340 km) stretch on the eastern DFC will be ‘commissioned’ in December. It will be followed by the Rewari-Marwar (452 km) stretch on the... read full article... Eastern DFC’s 340-km section may be commissioned in December
If its not the goof up of the media person and if this actaully happens even late by a month or two then its really a good news for passengers travelling via these routes.
This is correct reporting bhai. I did some research on Twitter and found this video posted from the project site near Aligarh. Looking at this video we can assume that this project is developing at super speed. EDFC Video report - click here
First May was target for Khurja bhaupur section Then August Then October And now December Why projects are treated as gambling where each media is taking one date as his stake to win or lose... more...
The focus should not be on false dates but full safety and speedy work
Important Note:This website NEVER solicits for Money or Donations. Please beware of anyone requesting/demanding money on behalf of IRI. Thanks. Disclaimer: This website has NO affiliation with the Government-run site of Indian Railways. This site does NOT claim 100% accuracy of fast-changing Rail Information. YOU are responsible for independently confirming the validity of information through other sources.