#ETALDELECTRIFICATIONUPDATES
#ELECTRIFICATIONSONTALAI
When i am travelling towards JBP from KYN via ET i have spotted work of electrification b/w ET-JBP section and also saw the work of doubling started in Bagratawa-sontalai section and i am happy to see that pace of work is very fast b/w ET-PPI section and around 95% work is completed between ET-PPI and work between PPI-NU is very slow but its good that in many places OHE holes has been digged and in some places work of digging OHE holes is going on so hopefully by this...
more... year mid we can expect OHE poles and wiring on PPI-NU section and on ET-PPI section only place remaining for fitting OHE pole is bagratawa bridge and even OHE poles with wires is being fitted before and after tunnel also and even hooks has been installed inside tunnel to fit OHE wiring also and spotted crew and wagons used for installing OHE and wires and hopefully they will be connecting the new line with the existing loop line before Bagratawa going towards NU and below is the details of pics-
1,2nd pic-Train stopped for crossing and spotted unfinished OHE wiring at sonatalai
3rd pic-shunting loco of OHE wiring van
4,5th pic-trees cutted to lay base for new BG line b/w sontalai-Bagratawa section and this work is started from sontalai end.
6,7,8,9,10,11th pic-going towards tawa bridge and OHE poles with wires installed
12th pic- OHE pole installed till the tawa bridge entry from sontalai side.
13th pic- crossing Tawa river and no OHE poles on the bridge but can be seen soon.
15,16,17th pic-going towards tunnel and OHE poles with wires can be seen.
18,19,20,21st pic- Going towards Bagratawa station and OHE poles with OHE wires can be seen.
22,23,24,25th pic- Loop line starts before entering Bagratawa station and Hole digging work beside existing loop line is going on so may be this loop line will connecting to the new line once its been laid b/w sontalai-bagratawa
26,27,28,29th pic- spotted OHE wiring van with wires and other equipments on existing loop line before Bagratawa.
30-32nd pic- entering already wired Bagratawa station
33,34th pic- spotted Sabarmati WDG4 monster with goods rake waiting for green signal at Bagratawa station.
so these all information i got while travelling towrds JBP on 24th Dec,2016 so if any member have any new information's aftr 24th pls share