#ActEast: Set to bring seamless connectivity to Mizoram!
🚉 Bhairabi - Sairang Railway Line (51.38 km) Project
📈Overall Progress: 87%
...
more... 🌉Bridge Works Completed
- Major: 5/55
- Minor: 75/87
-ROB/RUB: 6/9
⛰️Tunnels: 12600m/12853m
#RailInfra4Mizoram*As on 16 March'2023
Source: MOR Twitter Handle