Update on #GZBMBElectrification :
> OHE poles laid on both sides of Hapur Junction.
> HPU completely electrified.
> Initial work began between GZB and HPU with poles being laid on all halts en-route.
>...
more... Recently it has expanded on the other side of HPU towards Garhmukteshwar Bridge.
> Year end is the deadline for GMS-HPU stretch.
> ABSOLUTELY no progress between MB and GMS.
> Work on MB-GMS stretch will begin only after completion of the second overhead bridge.
>Work on GMS bridge in full swing. Basic structure ready. Track is yet to be laid.
> Mehrauli, Dasna, Pilkhua have poles laid but NO progress in between them.