Breaking News: ಬೆಂಗಳೂರು-ಮಂಗಳೂರು ರೈಲ್ವೇ ಹಳಿ ಕಾಮಗಾರಿ ಪೂರ್ಣ: ಮೊದಲ ಯಶವಂತಪುರ-ಮಂಗಳೂರು ಮೊದಲ ಪ್ಯಾಸೆಂಜರ್ ರೈಲು ಓಡಾಟAll trains running between Bengaluru and Mangaluru have resumed their regular schedules. Train operations were suspended for 13 days due to a landslide on the Sakleshpur route. Over 500 workers worked tirelessly to repair the track despite continuous rainfall. The first passenger train successfully ran on this route at 12:37...
more... PM on August 8th.
Bengaluru aur Mangaluru ke beech chalne wale sabhi trains apne schedule par vapas aa gaye hain. Sakleshpur route par landslide ki wajah se 13 dinon tak train service band thi. Barish ke bich 500 se zyada workers ne track repair kiya. Pehli passenger train August 8th ko dopahar 12:37 pe...
more... chalti hui dekhi gayi.