Mumbai Metro 3 Progress Update: Completion Expected By End Of December 2024The first phase of Mumbai Metro 3, running between SEEPZ (Santacruz Electronics Export Processing Zone) and Bandra Kurla Complex, is now scheduled to be completed by the end of December 2024. This was initially scheduled for September 2024. The Maharashtra Cabinet has approved a direct payment of 1163 crores to the...
more... Mumbai Metro Rail Corporation for the project, which is currently 98.1% complete. The total cost of the project is Rs 37,275.50 crore.
Mumbai Metro 3 ka pehla phase, SEEPZ (Santacruz Electronics Export Processing Zone) aur Bandra Kurla Complex ke beech mein chalega, December 2024 ke end tak complete ho jaayega. Pehle yeh September 2024 mein complete hone wala tha. Maharashtra Cabinet ne Mumbai Metro Rail Corporation ko project ke liye 1163 crore ka...
more... direct payment approve kar diya hai, jo abhi 98.1% complete hai. Project ka total cost Rs 37,275.50 crore hai.