Physical Progress - 75%
ЁЯФШLength- 159.81 Km.
ЁЯФШLand acquisition completed- 11.39/ 16.45 Hectare (70%)
A)Completed section: 72.68 km (45.47%)
Nandgaon- Manmad
Jalgaon- Pachora
B) Near Completion section: 31.79 km (19.89%)
Chalisgaon- Pimperkhed
C)In Progress section : 55.34 km (34.64%)
Pimperkhed- Nandgaon
Chalisgaon- Pachora
ЁЯЯвIn Progress Works-
тШС Earthwork - 34.10/59.92 Lcum. (57%)
тШС Blanketing- 0.94/7.42 In progress. (13%)
тШС Important bridgesтАУ 1 in progress. (40%)
тШС Major BridgeтАУ 11/21. (52%)
тШС Minor Bridge/LHS/RUB- 142/295. (48%)
тШС Station Building- 7/15 (47%)
тШС Track linking тАУ 70/ 160 Tkm (43%)
тШС Ballast Supply- 2.87/ 5.02 Lcum (57%)
тШС Overhead Equipment OHE Foundations -774/3168. (24%)
тШС OHE Mast Erections -513/2443. (21%)
тШС OHE Wiring- 18/160 km (11%)
ЁЯФ┤Completion of this new 3rd line will reduce congestion on busy Mumbai- Howrah route and will improve mobility of the trains.
ЁЯФШProgress of doubling/3rd/4th new lines all over Central RailwayтАЩs 5 divisions-
ЁЯФШCR has completed 161.80 km multitracking (new line/doubling/3rd/4th line) in current FY from April 2023 till date 2023.
ЁЯФШ3890 Crs planned by CR in this year for new lines/doubling/3rd/4th line.
ЁЯФШ2990 Crs expenditure done till date