(i) Mahesana- Bhandu Motidau (7.89 Km) - Earthwork (90%), Minor bridges (90%), Major bridges (90%) completed. 3 Km track Linking completed. Platform work at Bhandu Moti Dau is in progress(30%).
(ii) Palanpur – Dharewada (24.19Km)-Dec-23: Earthwork (0.53/1.5)(35%), Important Bridge (1/1)(70%) & major bridges (1/1)(5%) completed.
(iii)...
more... Dharewada -Kamli (11.87Km)-Jan-24: Earthwork (35%), Blanketing (.02/.36)(5%), Important Bridge (1/1)(60%) completed.
(iv) Kamli-Bhandu Moti (21.15 Km)-Feb-24: Earthwork (60%) completed. Physical Progress: 25%
TDC : (i) Mahesana- Bhandu Motidau (7.89Km) : July 23 (ii) Palanpur- Dharewada (24.19Km) : Dec 23 (iii) Dharewada- Kamli (11.87km) : Feb 24 (iv) Kamli-Bhandu Motidau (21.15 km) : Jan 24