Electrification is going ahead..🤞🤞🤞
Statutory inspection of RE works followed by speed trial at full sectional speed(100 Kmph) in Purnea–Jogbani(79.23 RKM/106.96TKM)single line section of Katihar Div. of NFR completed successfully. With this total commissioning by CORE during (2022-23) is 2758.3RKM/3783.94TKM
Courtesy....... NFR Twitter Handle.