Jiribam - Imphal Project in Manipur has achieved physical progress of 91.78%. It is a crucial project for Northeast connectivity and shall become a new lifeline for the people of Imphal.
Works Completed till 30.11.22:
•...
more... Tunnels - 48/52
• Major Bridges - Substructure of 7 & Superstructure of 5 out of 11
• Minor Bridges - 110/129
• Stations - 6/11 constructed