Electrification progress on Moradabad - kashipur - Ramnagar route
Moradabad - Got outer :- Electrification is complete.
Got outer - Kashipur outer :- Foundation work complete, Poles erected, brackets placed and wiring not done.
Kashipur...
more... :- Foundation work complete, Poles started placing in foundation and in some place poles also erected.
Kashipur outer - Ramnagar outer:- Foundation work complete, Poles erected, brackets placed and wiring not done.
Ramnagar :- Foundation work complete, Poles erected but wiring not done.
This is the progress of electrification on Moradabad - Ramnagar route.
SSP details:-
Pipalsana SSP will complete finishing going on.
Roshanpur SSP will completed.
Kashipur SSP work has not started.
Ramnagar SSP work has not started.
Note :-
Wring train with wire has reached at Kashipur junction within a week wiring should started i think.