6th Line Work is Going at Good Pace Between Goregaon to Bandra
Goregaon to Ram mandir land has been cleared and bridge work on Oshiwara Nalla have started
Bridge work Near Jogeshwari also have started
Jogeshwari...
more... Old sub station has been demolished and land has been leveled
Jogeshwari to Andheri Stretch the old boundary wall has been demolished and the land for 6th line is now visible
Pilling work Near Andheri Subway for bridge also have started
Demolishing work of Old Railway Colony at Vile parle in good pace
Land has been levelled in Band yard and also beside the Loco Trip shed at bandra for extension of the line