Anantapur-Dharmavaram doubling update: anantapur to prasannayapalli land levelled but requires remodelling of anantapur yard. Prasannayapalli to zangalapalli some portion chips is spread and concrete posts laid, poles erected but some portion is unattended. Two major bridges are there. One bridge is almost completed and at another bridge prefabricated blocks in huge number are procured at site. Chigicherla-dharmavaram no signs of concrete posts, no sign of chips spread. Major bridge works not even started at Dharmavaram outer.