STATUS UPDATE ON SANKRAIL FREIGHT TERMINAL WORK AS ON 06.09.20
Construction work under phase- 1 of Sankrail Freight Terminal has already been commissioned. Other works viz. Ballasting, one Road Over Bridge, new approach road and electrical are in progress in full swing. Loading wharf of line no.8 for unloading of steel consignments has already been completed and loading has started since 15.08.2020.
...
more...
Source SER FB
Where is this situated? Nowadays IR is giving high importance to Freight business, good for revenue generation.