Chittorgarh nimach #Eletricfication Update
1. Chittorgarh Gambhiri Road Outdur 90% Complete patch work due and Wiring done.
2. Gambhiri Road nimbahera 60 % complete poles 70 % done wiring work due.
3. Nimbahera outside to nimach work 99% complete.
10km...
more... ka kam Baki rah gya
I think Feb me work pura hona mushkil hai kyu ki shambhupura or nimbahera KE bich dubling ka kam me non interlocking hone KE bad hi Eletricfication pura hoga or interlocking hone me 15 din lagne Wale h So ab
#CRS march me hone ki puri umeed hai