ELECTRIFICATION UPDATE DECEMBER 2019
*Madgaon-Kumta-Bhatkal section*
*Madgaon-Harwada* - Foundation work started at Balli
*Harwada* - Foundation work complete on PF and outer
*Harwada-Ankola* - No work
...
more... *Ankola* - Foundation work complete on PF and outer
*Ankola-Gokarna* - No work
*Gokarna* - Foundation work complete on PF and outer.
*Gokarna-Mirjan* - no work
*Mirjan* - Foundation work started.
*Mirjan-Kumta* - Foundation work completed post Aganashini river
*Kumta* - Foundation work completed, Main Masts and poles have been erected,drop down masts and Cantilever yet to be installed.
*Kumta-Honnavar* -poles erected but not fixed.
*Honnavar* - Poles erected and fixed,cantilever yet to be installed.
*Honnavar-Manki* : Foundation work completed ,some poles erected and fixed.
*Manki* : Poles erected and fixed.
*Manki-Murdeshwar* : Poles erected and fixed.
Murdeshwar: Loose wiring done.
*Murdeshwar-Chitrapur* : loose wiring done.
*Chitrapur* : poles erected and fixed,cantilever assembly installed,wiring in progress
*Chitrapur-Bhatkal* : Wiring in progress.
*Bhatkal* : Loose wiring done.
*Traction Sub Stations*
*Balli* - Foundation and building work started
*Karwar* - Not Commenced
*Kumta* - Foundation work has begun,one transformer arrived at site.
*Murdeshwar* - Foundation work started
*Sectioning Posts*
*Gokarna* : Foundation and building completed poles to be installed
*Honnavar* : Foundation and building completed poles to be installed
*Bhatkal* : poles and interrupter installed,wiring pending
*River bridges*
Poles erected on Aganashini,Gangavali and Sharavathi rivers