#PuneSolapurGulbargaDoubling
Detailed status of doubling and electrification of Pune - Solapur section.
As a part of Solapur - Daund doubling, day before yesterday CRS completed between Wadshinge and Bhalawani.
As per the current status, Bhalawani and Dhavalas stations will be fully operational from today. Work at Wadshinge is already completed. Kem station will be operational from 29 Aug, as existing main...
more... line should be realigned to accommodate new UP Main Line. As of now, only down side loop line is operational at Kem. At Kurduwadi Junction, major remodeling work is completed. Some minor works are remaining.
Disappointing thing at Kurduwadi is after realignment Pandharpur line will be branch line from UP Main line at Pune outer as shown in the video. It should be separate line coming from PF1 of Kurduwadi to ease the operation.
From Kem to Madha, foundation base for installing poles are created on both lines. Poles are also installed near Kem.
PFB sequence of doubling images.
1. Caution board at Bhalawani.
2. New line at Bhalawani ready for operation.
3. Bhalawani new TB
4. Temporary tents installed at outer of all stations consist of ASM for ease of operation.
5. Middle line is closed for changing alignment at Kem.
6. Another view of Kem Station after doubling (middle line in the image is new line).
7. Electric poles installed on Kem - Dhavlas section.
8. New TB of Dhavlas Station.
9. UP Main line and new loop line is ready for operation.
10. New signaling system will be operational from today.