Hosapete-Hubballi 143kms Railway Double Electrification update:
*pic1-poles with insulators near TB river Bridges
*pic2-poles near Munirabad LC
*pic3-poles at munirabad RS
*pic4 poles near LC 81 HPT from here poles fixing work started at 141.0km...
more... till 101.0km near bhanapur
HPT-Bhanpur =40kms RE work likely complete in two months.
Note : all pics are btn HPT -MRB stations & all pics captured by myself