Hello Dear IRI Members, My City is gearing up for the grand Welcome of all Pilgrims visiting for Kumbh 2019. I want to request you to guide all pilgrims who may be your friends, relatives, neighbors or colleagues about the pains and inconveniences, city people has taken to make them feel satisfied and to make city more developed. See even, After PM has inaugurated completed projects worth 4000 crores on 16 Dec 18 at Prayagraj. Still some projects is in pipeline and will finish shortly. Have a look at upcoming railway projects completion...
Details of Pics:
Pic1:...
more... From NR track at Rambagh, see NER track (with brown red new copper wire on poles) just electric wired.
Pic2: Under Rambagh ROB, Ald-Prg track work started on sleepers for doubling.
Pic3: Junction point of NCR, NR & NER near Ald Stn east end (See the west end of just electric wired Ald-Aly NER line and neutral section for 10-12 metres)
Pic4: Construction of more rest-houses for pilgrims near Plt 1 of Ald
Pic5: See the 6 lines in Pic at Ald east end, Left two lines going to NR, Right three of NCR and the middle one is NER line (Ald-Aly), just electric wired.
Pic6: 200 mtrs long gadha line (Platform 5) between Platform 4 & Platform 6, which remains, mostly unused. So this short platform will be unnamed and merged with Platform 4 and platform 6 now will be renamed as Plt 5 and newly made platform in north side will be named no. 6
Pic7: NER track (Newly electric wired), first electric pole visible from Ald east end.
Pic8: one more pic of 200 mtrs gadha line (Platform 5) which is going to be unnamed and merged with Platform 4
Pic9: Track laying work on sleepers for Ald-Prg doubling, status todate (Rambagh ROB visible at distance)
Pic10: Kumbh Pilgrims Passeger-Rest-House No. 1 near Ald Plt 1
Pic11: Finishing works at New Platform at Ald (It will be named as Platform 6, when Plt 6 will be renamed as Plt 5 after unnaming only 200 mtrs long existing Plt 5 and merging it with Plt 4)
Pic12: Kumbh Pilgrims Passeger-Rest-House No. 3 near Ald Plt 1
Pic13: Platform 5 finishing at Aly (Rambagh) Station. Renaming can be done here also as starting from south Platform 1, then Platform 2&3, then Platform 4&6 and now this Platform 5 in northernmost will become topsy-turvy (ulta-fulta)
Pic14, 15 & 16: New Platform under construction at ACOI towards North (Entry Point). Same problem here. Platform 2&3 in south end, then single-side Platform 1 in middle, then ndls-hwh two main lines and then, in the northernmost side, this new platform, here also, all platforms naming have to be done again to avoid confusion (when this platform gets ready).
Pic17: New Station building (including dormatories, Rest house, RPF rooms) being constructed at ACOI
Pic18: All poles under wires now (for Ald-Aly electrification)
Pic19: TBM Machine at ACOI, Picking Ballast from tracks, filtering sand+soil+dust from it and re-dropping cleaned ballast (gitti) at tracks, assisted by few gangmen.