THE LAST LINE (diesel main line) BRANCHING FROM VILLUPURAM IS GOING TO GET ELECTRIFIED,This is somewhat sad news for diesel fans ,hope they enjoy diesel end to end from chennai for few years! Ok coming into the progress given by MAYURAM KUMAR SIR
Members, Yesterday I went to Chennai in chendur express and returned in the same. I amazed to see that pole foundation digging and completed pole foundations in between TDPR & VM. I cannot believe that. The following pictures were taken while going to Chennai between TDPR & VM. All the photos are showing the east side of the line. The works are going on in full fledge – 4G speed!
But...
more... the works are not started in stations. On the whole nearly more than 50% length of TDPR – VM line is seen with completed pole foundations and pits.
In both sides the poles come. So what about the second line between CUPJ & TDPR? While taking KIK – TJ electrification all the poles are in one side(north and west side( KIK – NGT)).
Let us come to the substations. In MV as I told earlier the substation comes in north west side of the station. For that the goods shed colony houses have recently demolished. So the land for substation is ready at MV.
PC : MAYURAM KUMAR (Ir southern discussion zone)