Electrification update from Pakur to NFK.
Wiring work complete from Pakur side till Gumani. All civil work and poll erection work complete till NFK. Wiring work on in the section. Hope full of witnessing electric locos in the section soon.
Pic 1: Electrification work at Gumani station
Pic 2: Electrification work at Bonidanga station
Pic...
more... 3, 4 & 5: Electrification work near Tildanga station
Pic 6 & 7: Wiring at NFK station, the wires being temporarily bonded with binding wire before being bonded by cooper wires.
Pic 8 & 9: Men at work on wires at NFK with trains passing below them