Delhi - Rewari - Jaipur Electrification:
May 2018 Status
-----
GGN Gurugram Rly Stn
--
Elec foundation works finished
Elec Poles are PLACED 90%
Elec Poles are FIXED to foundation 70%
Elec Portals are PLACED 50%
Elec Portals are FIXED to foundation 40%
Elec Poles/ Portals where cantilever assembly FIXED 0%
-----
GGN Gurugram - BDXT Basai Dhankot
--
Elec foundation works finished
Elec Poles are FIXED to foundation 90%
Elec Poles/ Portals where cantilever assembly FIXED 80%
-----
BDXT Basai Dhankot Halt Stn
--
Elec foundation works finished
Elec Poles are FIXED to foundation 90%
Elec Poles/ Portals where cantilever assembly FIXED 80%
-----
---------------------