#Electrification** OHE Tightening works are at full swing all over GGN, DEC, PTNR, DEE tracks
This may take about 15 days as it is being done without line block
** Feeder line works are in progress in Garhi Harsaru TSS and Patel Nagar PTNR SP Sectioning Posts
** TSS Traction Sub Station setup at Garhi Harsaru is pending which is in last stages
** This may take 15 days
** Even after energising from TSS to Track OHE, few track trials would be done with OHE inspection cars and then pre-CRS trials with Electric Loco in both up and down tracks ....
** Also, tests would be done with Elocos with higher and lower pantos as High Rise OHEs are installed in GGN Gurugram - RE Rewari section ...
** In my guess, CRS would be surely after Jan 15, 2019 ....
---------------------
rojaRAJU, O+
===========