Delhi - Rewari - Jaipur Electrification:
Dec 2018 Status
-----
** Till now, in DEE Sarai Rohilla, Main line between PF 1 and PF 2 was NOT Electrified .... By this project, even this line also is wired... It connects to the last line in DEE DBSI Daya Basti which turns to PTNR Patel Nagar ...
** In DEE Sarai Rohilla, Ashram comes in PF 1 and Double Decker departs from PF 3; So Ajmer Shatabdi passes through the 'till now' unwired pass through line between PF 1 and PF 2;
** OHE works of last line completed between PTNR Patel Nagar - DBSI Daya Basti - DEE Delhi Sarai Rohilla
** Last line is with old and new OHE portals/ posts ... Old poles/ portals are dull coloured but new poles/ portals are bright white coloured ... Both are
interspersed ... Old poles hold OHE wires of main line and new poles hold OHE wires of last line which was left unfinished in Patel Nagar - Daya Basti - Sarai Rohilla stretch
** OHE tightening/ finishing works pending
-----
DBSI Daya Basti Halt - DEE Delhi Sarai Rohilla
--
Elec foundation works finished
Elec Poles are FIXED to foundation 100%
Elec Portals are FIXED to foundation 100%
Crossbeams for Elec Portals FIXED 100%
Elec Poles/ Portals where cantilever assembly FIXED 100%
Wiring completed 100%
OHE calibrating to centre and fastening 20%
-----
---------------------