Delhi - Rewari - Jaipur Electrification:
May 2018 Status
-----
PM Delhi Palam Rly Stn
--
Elec foundation works finished
Elec Poles are FIXED to foundation 90%
Elec Portals are not found
-----
PM Delhi Palam - SMDP Shahbad Mohammadpur Halt Stn
--
Elec foundation works finished
Elec Poles are PLACED 90%
Elec Poles are FIXED to foundation 60%
Elec Poles where cantilever assembly FIXED 10%
-----
SMDP Shahbad Mohammadpur Halt Stn
--
Elec foundation works finished
Elec Poles are PLACED 90%
Elec Poles are FIXED to foundation 80%
Elec Poles where cantilever assembly FIXED 0%
-----
---------------------