ET- ALD Electrification update
Date:- December 11, 2016
NU/Narsinghpur-ET/Itarsi Electrification update (Part of ALD/Allahabad-ET/Itarsi Electrification):-
I Traveled from Kareli to Mumbai by 12062(Till ET) + 12162(from ET), Yesterday.
Narsinghpur to Kareli updates given by my...
more... brother, sorry due to fog and cold, not able to capture pictures.
Between Stations (Excluding Platforms area/Till Outer)
Narsinghpur- Kareli = Poles are established till baskheda-Kathotiya road railway gate, no wiring, hole work completed
Kareli-Bohani=Hole work completed, no poles
Bohani-Gadarwara= Hole work completed till Manakwara(Kareli- Gararwara road) railway gate, no poles
Gadarwara-Salichoka road =no poles, no hole work (no electrification Sign)
Salichoka road-Bankhedi = no poles, no hole work (no electrification Sign)
Bankhedi-Pipariya= Hole work completed, no poles
Pipariya-Sohagpur= Poles established, wiring work is in progress
Sohagpur-Guramkhedi= work completed
Guramkhedi-bagratawa= work completed
Bagratawa- Sontalai= poles established till tunnel from BGTA, work is under progress inside of tunnel
Sontalai-Gurra= work completed
Gurra-Itarsi=work completed till itarsi outer, BPL-JBP Division border Board
Station wise (only on Platform, between JBP end to Itarsi end):-
Narsinghpur= poles established wiring work is in progress
Kareli= no poles, hole work completed
Bohani= hole work completed, poles establish work under-progess
Gadarwara=no work (no electrification Sign)
Salichoka= no poles, hole work completed
Bankhedi= no poles, hole work completed
Pipariya= poles established, wiring work is in progress
Sohagpur= pole work under progress
Guramkhedi= work completed
Bagratawa= pole work under progress
Sontalai= pole work under progress
Gurra= work completed
TSS work is also running with full speed.
I think , may be that news will become true, that from JAN 2017, E-Locos will there between PPI-ET.