#JBPGBGPROJECTUPDATES
#SECRGMVISITSSOYNIRSECTION
Good to see SECR GM is taking spl interest in completing JBP-BTC BG project soon and as part of his inspection GM and other oficls of SECR visited SOY and inspected SOY-NIR BG works and GM sply said to Ofcls that unlike delay in opening of JBP-SOY BG line there shud not be any delay shud happen to complete work on SOY-NIR BG section and Work shud be completed with March 2017 anyhows including works of stn. and surrounding areas and every months the progress report shud be submitted...
more... to GM to followup with the pace of work of SOY-NIR section so very good decisions by SECR GM and it will pace the ongoing BG work b/w SOY-NIR section and trains can ply from JBP-NIR within APR/MAY 2017 after CRS approval