on 5th dec I travel from hosapete st to hubballi i saw work of HPT-UBL doubling work =143km so here it goes
1.hpt -mrb(first three pics shows work on this) =6.1 km :work is going on ...constructing bridge across tunga bhadra river is imp taskin this project & more no of canals pass threw these stations.. construction of concrete bed as start but yet to start ground leveling work..
2.mrb-ginigera= 11km : about 4km they laid sleeper beds but remaining 7km they r working on ground leveling as u can see in...
more... 4th pic
3.ginigera-koppal=11km:work is gud ground leveling is completed they laid sleeper beds but yet place tracks.. 75% work competed.. as u can see in 6th pic
4.koppal - harlapur=39km: work is awesome they hv completed most of work like ground leveling, placing sleeper beds & placed track on it... 85% work completed ..u can it in 5th pic
5.harlapur- navalgud rd =49km: work is gud ..ground leveling completed , laid sleeper beds & placed track on it expect few place near hulkoti is slow pic 7th
6.navalgud rd -hebsur=8km: about 4km work completed yet remaining 4km work to complete pic 8th ground leveling
7. hebsur - ubl=19km : while as u already know ther exists double line btn these st ..