#ElectrificationUpdate #08November2019
DAL/DaliGanj Junction - STP/Sitapur Junction electrification update
Poles - 100%
Brackets - 93% done (Completion expected by 16-Nov-2019)
Wiring - Initiated on 31-Aug-2019 at MBP/Mohibullapur. From DAL/DaliGanj Junction wiring started leaving one...
more... patch for final linking with existing live wire. As per latest update wiring reached till KB station (Wiring at IJ station only will begin from 09-Nov-2019) moreover OHE van has already started from DAL end and completed till BKT outer (Wiring completion expected by 23-Nov-2019 or so).
SSP - 3 SSP's been located at BKT, SD and STP. Two transformer has been placed at BKT SSP rest nothing much has progressed (Completion expected by Dec2019 or so)
Block - 4 hours block been requested at DAL and STP respectively for connecting with existing live wire. More info awaits.
OHE wire energized - Expected by end of Nov2019 or starting of Dec2019
Trial run : First trial run would be on 29-Nov-2019
CRS inspection - Expected by Dec2019
Commercial uses - Any point of time after successful CRS
** All completion dates are tentative**