#ElectrificationUpdate #09December2019
DAL/DaliGanj Junction - STP/Sitapur Junction electrification update
Poles - 100%
Brackets - 100%
Wiring - 99%
OHE...
more... van - Currently finalising at STP/Sitapur Junction
SSP - 2 SSP's been located at SD and STP. At STP 80% work has been completed (Completion expected by end by 20-Dec-2019). At SD 60% work has been completed (Completion expected by end by Dec2019 or so).
SP - Basic structure completed and two transformer has been placed at BKT (Completion expected by 2020).
Block - On 08-Dec-2019 at STP 6 hours block been taken and new line coming from DAL side has been connected with existing live wire of BUW-STP line. In today's (09-Dec-2019) block wiring at station line has been connected with existing live wire towards ROZA. Tomorrow block will start at 13:30 to finalised any pending work.
OHE wire energizing - Post block completion
Trial run : First trial run expected on 22-Dec-2019
CRS inspection - As per newspaper 26-Dec-2019
Commercial uses - Any point of time after successful CRS and permission granted by traffic department.