Ratlam chittorgarh #Eletricfication update today.
1. Ratlam to Mandsore #crs Successful
2. mandsore to nimach 90% work complete only sub station And CRS Inception work due.
3. nimach to jawad road work 98 %completed
4....
more... jawad road to nimbahera poles work complete only wiring work due.
5. nimbahera to chittorgarh foundation work 95 % complete and poles work 35% complete , no wiring
* almost 189 km me se 150 km work pura ho gya h ab 40km ka kam baki h or doubling line me shambhupura se nimbahera tak bridge work 95 % and complete track 75% complete. nimbahera to nimach no progress
kota chittorgarh
#Eletricfication 1 kota to bundi poles work pending foundation completed