CNA-COR electrification :- Wiring work has been completed by WR on Ghosunda - Chanderiya line and in progress on Chanderiya - Chittaurgarh railway station....
Pic No.1-3 :- Complete wiring work on GSD-CNA bypass line.
Pic No. 4 :- Wiring work pending on track used for goods train just before starting platform no.1.
Pic No. 5-6 :- Train No. 09722 UDZ-JP Holiday SF...
more... arrived on platform no.1.
Pic No. 7-8 :- Wiring work completed on platform no.1 & main line.
Pic No. 9-10 :- Newly built foot over bridge has been started.
Pic No. 11 :- Second entry gate & ticket Window is ready to serve passengers.
Pic No. 12 :- Workers working near COR on OHE wires.
Pic No. 13-16 :- Complete wiring work on platform no.1&2.
Pic No. 17-20 :- 3 new tracks are now ready to reduce traffic load on COR.
Pic No. 21-22 :- Wiring work completed on platform no.3 but pending on new track.
Pic No. 23 :- Foundation for laying down stairs to connect FOB near Ratlam side is completed on platform no. 4&5.
Pic No. 24 :- Main entry gate of COR station.