Ghazipur News: फरवरी के अंतिम में नई रेल लाइन का होगा ट्रायलThe CPM of Rail Vikas Nigam Limited (RVNL), Vikas Chandra, inspected the new 7 km long railway line between Sonwal and Ghat, costing around 200 crores. He visited the under-construction Ghat station to review ongoing development works. He instructed his team to complete all remaining work by February to ensure trial...
more... runs and load testing can be conducted in the last week of February. The Commission of Railway Safety (CRS) is scheduled to inspect the line on March 6th. The CPM traveled by motor trolley along the new line, emphasizing the completion of all work by February. The 9.6 km first phase from Sonwal to City Station has already undergone CRS and other tests. The new route will be operational after CRS clearance and the project's inauguration is tentatively scheduled for March by the Prime Minister.
Rail Vikas Nigam Limited (RVNL) ka CPM, Vikas Chandra, Sonwal se Ghat tak ki 7 km lambi nayi rail line ka inspection kiya. Ye line almost 200 crore ki hai. Ghat station pe unhone ongoing development work ka jaayza liya. Unhone apne team ko February tak saare remaining work complete karne...
more... ka order diya. Unhone kaha ki February ke last week mein nayi line pe trial run aur load testing hone chaiye. Commission of Railway Safety (CRS) March 6th ko line ka inspection karega. CPM motor trolley pe Ghat se Sonwal tak nayi line ka different jagah pe inspection kiya. Unhone kaha ki February tak saare remaining work complete karne chaiye. Pehle phase mein Sonwal se City Station tak 9.6 km lambi line CRS aur other tests already complete ho gayi hai. CRS clearance ke baad ye new route operational ho jaayega. Project ka inauguration March mein PM karenge. Ab tak date fix nahi hai.