🟠In progress works-
➡️East Side station building- column casting upto plinth level
➡️Quarters staging for slab casting & Column casting
➡️West Side sheet fixing work in progress
🟢Completed works-
✅Soil investigation
✅Site lab
✅Labour hutment
✅Dismantling of 23 old quarters & abandoned structures
✅PCC & Foundation work, Column casting
✅Excavation of East Side station building
✅Batching plant installation & calibration
✅Safety park installation
✅Extention of west side parking
Indian Railways is committed for gradual improvement of amenities for our passengers.
please wait...Translate to EnglishAdmin Moderator Source Cr X Handle
CRInfraUpdates
AJNI Station Major upgradation redevelopment (Nagpur div).
By RLDA (Rail Land Development Authority)
Cost- 297.79 Crores
In progress works-
East Side station building- column casting upto plinth level
Quarters staging for slab casting & Column casting
West Side sheet fixing work in progress
Completed works-
Soil investigation
Site lab
Labour hutment
Dismantling of 23 old quarters & abandoned structures
PCC & Foundation work, Column casting
Excavation of East Side station building
Batching plant installation & calibration
Safety park installation
Extention of west side parking
Indian Railways is committed for gradual improvement of amenities for our passengers.