✳️ Karjat-Extension of yard line connecting UP yard to Karjat – Panvel line and 4th line between Karjat - Palasdhari.
💲Cost – 74.53...
more... Cr.
✳️Overall Physical Progress – 60%
✳️ Scope of work-
➡️Increase in length of EMU stabling line no. 1, 2 & 3.
➡️Increase in length of Reception and Dispatch line No. 2,3,4,5 & 6.
➡️Provision of one new Reception and Dispatch line No. 7
➡️Segregation of Karjat -Khopoli line from Khopoli- Lonavala main line.
➡️Provision of Foot Over Bridge (FOB) at Kalyan end & Lonavala end.
➡️4th line between Karjat and Palasdhari.
✳️Completed works-
➡️Extension of 8 minor bridges have been completed.
➡️Contract for earthwork has been awarded
➡️Ballast supply has been completed.
➡️Earthwork of Reception and Dispatch lines completed.
➡️Work of stabling siding no.3 completed.
➡️Work of relocation of 2 stabling line completed.
➡️Foot Over Bridge at Lonavala end completed & Commissioned.
➡️Indoor wiring completed and Outdoor wiring work 80% completed.
✳️Work In Progress –
➡️Work of Foot Over Bridge is in progress at CSMT end
➡️Earthwork for Reception & dispatch line no. 7 work is in progress.
➡️Track work of Palasdhari line is in progress.
➡️Work of siding no. 1 is near completion.
➡️Signaling wiring Testing in progress.
🛑Completion of this work will improve mobility of trains in Karjat yard and Lonavala-Palasdhari Karjat Section.