Permission of BNI/NI at MTB on SRE-MB section for commissioning of UP Loop Line.
The details of PNI/NI period:-
Station/section | MTB (Matlabpur) | (SRE-MB) | Double line Electrified Section
BNI...
more...
08 days (Up line & DN) | 20.10.23 to 27.10.23 | (D-8 to D-1) (22.30 hrs.)
NI
04 days (Up & DN both) | 28.10.23 to 31.10.23 | D Day to D+3(17.30 hrs.)
TOTAL
12 days | (40.00 hrs.)
Coaching repercussions:-
Cancellation:-
1. 04301(MB-SRE) JCO 28.10.23 TO 31.10.23(4 trips)
2. 04302(SRE-MB) JCO 28.10.23 TO 31.10.23(4 trips)
3. 04359(CH-RKSH) JCO 28.10.23TO 31.10.23(4 trips)
4. 04360(RKSH-CH) JCO 27.10.23 TO 30.10.23 ( 4 trips)
Regulation
1. 15933(NTSK-ASR) JCO 24.10.23 regulate 30” enroute
2. 22355(PPTA-CDG) JCO 25.10.23 regulate 60” enroute
3. 12369 (HWH-DDN JCO )26.10.23 regulate 30” enroute
4. 12327(HWH-DDN) JCO 27.10.23 regulate 60” enroute
5. 12326(NLDM-KOAA) JCO 28.10.23 regulate 30” enroute.
6. 22355(PPTA-CDG) JCO 29.10.23 regulate 120” enroute
7. 12369(HWH-DDN) JCO 29.10.23 regulate 90 “ enroute
8. 22317(SDAH-JAT) JCO 30.10.23 regulate 120”enroute
9. 12318(ASR-KOAA) JCO 31.10.23 regulate 30” enroute
Freight trains repercussions: - Freight trains and late running trains will be regulated/Diverted accordingly.
Note: - 20 KMPH speed restriction is required in up line from D-8 i.e from 20.10.23 for preparatory works in up line.