✅At present Kala Akhar station has 2 mainlines and 1 loopline.
➡️Construction of 3rd mainline and 2 more new looplines in full swing.
Earthwork & levelling work completed.
Brief of Nagpur-Itarasi 3rd line-
➡️Length- 297.05 km
➡️Cost- 2449.91 Crores
➡️Expenditure till date- 1022.40 Crs
➡️Overall physical progress- 40%
A) Completed section- 31.62%.
Chinchonda to Kohli- 93.95 km
B) Near completion section (likely Commissioning in this Financial year)- 7.56%
Kohli to Bharatwara- 22.46 km
C) In progress works- 180.64 km (60.82%)
Chichonda to Itarasi- 167.80 km
Bharatwara to Nagpur- 12.84 km.
🛤 Completion of this line will reduce congestion of this Nagpur-Itarasi-Bhopal busy route and will improve mobility of trains.