#update10
Electrification progress on Moradabad - kashipur - Ramnagar route
Moradabad - Got outer :- Electrification is complete.
Got outer - Pipalsana outer :- Foundation work complete, Poles erected, brackets placed and wiring not done.
Pipalsana...
more... - Kashipur outer :- Foundation work complete, Poles erected, brackets placed and wiring done but not finalized.
Kashipur :- Foundation work complete, Poles erected, brackets placed and wiring done on 5 & 6 line .
Kashipur outer - Ramnagar:- Foundation work complete, Poles erected, brackets placed and wiring done but not finalized.
This is the progress of electrification on Moradabad - Ramnagar route.
SSP details:-
Pipalsana SSP completed
Roshanpur SSP completed.
Kashipur TSS work completed.
Ramnagar SSP work completed.
Got SSP completed
Note :-
Wiring has reached Kashipur towards pole no 49/2.