The Biggest Surprise of 2022 for Adra Divison.
Finally all the land hurdles of khana bowaichandi route has been eliminated.
The 76 land looser candidates has been found provisionally eligible and they are called for physical verification.
With this , the land accusations stands at 100% and work will be begin soon as the tenders for this project already awarded before....
more...
Project Current status - Pillars at damodar river already completed.
Patch earthwork completed between khana to damodar river.
Current progress - 20%
please wait...Translate to EnglishY'all won't believe the dope news for 2022 in Adra Division. Finally, all the bullshit land issues with the khana bowaichandi route have been sorted out. The 76 unlucky folks who lost their lands have been given the green light and are being called in for some physical verification. With this, the land situation is now 100% sorted and we can get this show on the road since the tenders for the project have already been approved. At the moment, the damodar river pillars are fully done and the earthwork between khana and damodar river is also complete. As of now, we're at 20% progress.
please wait...Translate to Hindi2022 ke liye Adra Divison ka sabse bada surpise. Akhir khana bowaichandi route ke saare zameen ke rok-tok door kar di gayi hai. 76 zameen haarne wale log provisional taur par eligible paye gaye hain aur inhe physical verification ke liye bulaya gaya hai. Iske saath hi, zameen ke ilzaam 100% tak pahunch gaye hain aur kaam shuru hone wala hai kyunki is project ke liye tender pehle se hi diye gaye hain. Project ke halat - Damodar nadi ke pillars pehle se hi poore ho gaye hain. Khana se Damodar river tak ki patch earthwork poorn ho gayi hai. Vartmaan mein progress - 20%.