Kalyan-Kasara 3rd line
of Mumbai division.
Length-67.35 km
Cost-792.89 Crores.
...
more...
A) Total land to be acquired- 49.23 Hectare
-Land acquisition completed- 35.96 Ha. (73%)
-Balance land acquisition- 13.27 Ha. (27%)
B) Completed works-
-Earthwork- 6.69 lakh cubic meter completed out of 17.43 lakh cu. mtr.
-23 Minor Bridges completed out of 205.
-OHE foundations- 200 completed out of 1400
-OHE Mast erection- 170 completed out of 1200
-Signalling cable shifting of Kalyan to Asangaon completed.
please wait...Translate to EnglishKalyan-Kasara 3rd line, bro! Mumbai division, you know? It's like, 67.35 km long and cost a whopping 792.89 Crores. Damn!
A) So, they gotta acquire a total of 49.23 Hectare of land, but they've already completed 35.96 Ha. That's like 73%. Still got 13.27 Ha to go, which is around 27%.
B) As for the completed works, they've done some solid progress. They've finished about 6.69 lakh cubic meters of earthwork out of 17.43 lakh cu. mtr. Not bad, right? Also, they've completed 23 Minor Bridges out of 205. They've done 200 OHE foundations out of 1400, and 170 OHE Mast erections out of 1200. Oh, and they also finished shifting the signalling cable of Kalyan to Asangaon.